Construction Contract Review Before Pricing | 12-Point Checklist

Use this 12-point construction contract review checklist to assess payment, delay, liability, and other risks before pricing and submitting your tender.

Construction Contract Review Before Pricing | 12-Point Checklist

How to Review a Construction Contract Before Pricing a Tender:

Before you price a construction tender, review the draft contract alongside the drawings, specifications, and bill of quantities. The contract determines who carries design risk, when payments become due, how changes are valued, and what happens if the project is delayed or terminated. Each of those terms can affect the price, the programme, or both.

For each risk you identify, decide whether to include an allowance in the price, request clarification from the employer, qualify your offer where the tender rules permit, or escalate the decision to management before committing to the bid.

Why Review the Construction Contract Before Pricing?

Once the tender price is set, it becomes harder to account for risks that were missed during the review. Extended payment terms can increase financing costs. An unclear scope can leave the contractor carrying work it never priced. A short notice period can affect the team’s ability to pursue an entitlement during delivery.

Arcadis’s 2021 report on construction disputes identified failure to understand or comply with contractual obligations as a leading cause of disputes in the Middle East in 2020. Reviewing the contract at tender stage gives the estimating, contracts, and legal teams time to identify those obligations and decide how to address them before submitting the bid. [1]

What Should a Tender Contract Review Produce?

A construction contract review should produce two documents the tender team can act on.

1. An internal contract risk register. Record the clause number, the issue, its potential cost or time impact, the decision needed, who owns it, and the deadline. Use the register to update the estimate and escalate risks that require approval.

2. A schedule of contractual deviations and clarification requests. Record the clauses that need clarification or amendment, explain the concern, and propose wording or ask a specific question. Share the schedule through the tender’s designated clarification process.

12-Point Construction Contract Review Checklist

1. Contract Documents and Order of Precedence

Gather the draft agreement, general and particular conditions, specifications, drawings, schedules, and tender addenda. Check which document takes precedence if two requirements conflict. Flag missing documents, inconsistent obligations, and provisions that need clarification before the estimate is finalised.

2. Scope of Work and Design Responsibility

Confirm what the contractor is expected to design, coordinate, test, commission, and deliver. Check who bears responsibility for the accuracy of site data and other information supplied by the employer.

Use a responsibility matrix to flag items that need technical verification, clarification, or a pricing allowance. Pay particular attention to obligations based on information the tender team has had limited opportunity to verify.

3. Payment Terms and Cash Flow

Check whether the contract uses a lump sum or remeasurement. Review how payment applications are submitted and certified, when payment becomes due, and how advance payments and retention are handled. For subcontracts, check whether payment depends on the main contractor receiving payment from the employer.

Model cash flow using the contract’s payment and certification periods. Include the cost of financing any gap between spending on the works and receiving payment.

4. Deductions and Set-Off

Identify what the employer or main contractor can deduct, whether the clause covers disputed amounts or claims under other contracts, and what notice or objection procedure applies. Seek clarification where the scope of set-off is broad or the procedure is unclear, and assess the effect on cash flow.

5. Variations and Change Orders

Confirm who can issue a variation, what form the instruction must take, and how additional work is valued when existing rates do not apply. Check how a variation affects the programme and how to request an extension of time. Clarify how urgent instructions will be authorised and recorded.

6. Delay Damages and Extensions of Time

Check the completion date, any binding milestones, and the grounds for an extension of time. Review the rate and cap for delay damages, whether separate amounts can apply to missed milestones, and how those amounts interact with the overall liability cap and other delay claims. Ask the legal team to assess how the relevant provisions apply under the governing law.

7. Notices and Claims

Record each notice deadline, the event that starts the clock, the authorised recipient, the delivery method, and the supporting documents required. Track the initial notice, the detailed claim submission, and any deadline for challenging a decision as separate steps. Assign responsibility for each one before the project starts.

8. Bank Guarantees and Bonds

Review the amount, wording, expiry, extension requirements, and release conditions for performance security and advance payment guarantees. Confirm the terms with the bank and legal team. Allow for fees, possible extensions, and the impact on available credit facilities.

9. Liability Caps and Indemnities

Check the aggregate liability cap, which claims fall within it, and which are excluded. Read indemnities and exclusions for indirect or consequential loss alongside the cap. Escalate any material exposure that needs a management decision or specialist legal review before the bid is approved.

10. Insurance Requirements

Review the required policies, coverage limits, deductibles, exclusions, and coverage periods. Confirm whether the policies cover the contractor’s design obligations and subcontracted work where required. Ask the insurance broker to confirm availability and cost before carrying those assumptions into the tender price.

11. Termination and Financial Entitlements

Review termination for default and termination for the employer’s convenience. Check notice and cure periods, how completed work and materials will be valued, and who bears demobilisation and outstanding supplier or subcontractor costs. Clarify how the final settlement and site handover will work if the employer terminates the contract.

12. Governing Law and Dispute Resolution

Identify the governing law, the court jurisdiction or arbitration agreement, and any steps the parties must complete before starting formal proceedings. Where arbitration applies, confirm the seat and rules. Check that the general and particular conditions describe a consistent dispute resolution process.

Reviewing Construction Contracts in the Gulf

The same checklist can structure a review in Saudi Arabia, the UAE, and other Gulf markets. The legal assessment still depends on the governing law, the type of contract, and the project. Identify whether the employer is a government entity or a private organisation, whether you are reviewing a main contract or subcontract, and which standard terms the particular conditions amend.

Ask the legal reviewer to check any mandatory rules relevant to the project, especially those affecting structural defects, liability, termination, and dispute resolution. Record the outcome so the estimating team can see which assumptions may affect the price.

Turn Contract Findings Into Pricing Decisions

Bring the risk register to the tender review meeting and agree what to do about each issue. For example, if the contract allows 60 days for payment after certification, estimate the cash flow gap using the expected certification period as well as the payment term. If the certification period is unclear, add a clarification request and record the assumption used in the estimate.
| Clause or issue | Potential impact | Tender action |
|---|---|---|
| Payment is due 60 days after certification | Higher financing costs if certification is delayed | Confirm the certification deadline and model the cash flow gap |
| Design responsibility extends to unverified site data | Additional surveys, design work, or programme risk | Clarify responsibility and price any agreed verification work |
| Variation valuation procedure is unclear | Additional work may be difficult to value or recover | Request a valuation procedure and confirm who can issue instructions |

How AI Can Support Construction Contract Review

A specialised AI tool can help the tender team organise its initial review by summarising key clauses, flagging potential risks, and identifying provisions that may need clarification or amendment. Jelani AI is designed for engineering and construction contracts and supports reviews in Arabic and English.

The contracts and legal teams should verify the findings against the draft agreement, its schedules, and any tender addenda before using them to approve the bid. Before uploading project documents, check the platform’s confidentiality and data-handling terms. Explore Jelani AI’s construction contract review features.

Frequently Asked Questions

When should you review a construction contract during tendering?

Start as soon as the draft contract and tender documents are available. This gives the team time to submit questions during the clarification period, assess the answers, and update the price before bid submission.

Does the review differ between Saudi Arabia and the UAE?

The main commercial review areas are similar, including payment, variations, delay, and liability. The legal effect of individual clauses can differ depending on the governing law, the contracting entity, and the nature of the project.

Can AI replace legal review of a construction tender?

AI can support the initial review and help teams locate and organise issues. The project’s contracts and legal teams should verify the findings and assess the commercial and legal implications before the company prices the risk or accepts the obligation.

This article is for general information and does not constitute legal advice on a specific contract.